8.1. The fees for an application for renewal, without modifications, of an authorization referred to in section 8 are as follows:
(1)  for a water withdrawal referred to in one of subparagraphs a to c of paragraph 1 of section 31.75 of the Act or in section 5 of the Water Withdrawal and Protection Regulation (chapter Q-2, r. 35.2) and with a maximum flow rate of less than 75,000 litres per day: $701;
(2)  for a water withdrawal with a maximum flow rate equal to or greater than 75,000 litres but less than 379,000 litres per day: $1,051;
(3)  for a water withdrawal with a maximum flow rate equal to or greater than 379,000 litres per day: $1,815.
However, where the application for renewal contains modifications to the conditions of operation of a water withdrawal to which section 30 of the Act applies, the fees set out in the first paragraph of section 8 are payable.
M.O. 2015, s. 1; M.O. 2016, s. 8; M.O. 2019-08-28, s. 6.
8.1. The fees for an application for renewal, without modifications, of an authorization referred to in section 8 are as follows:
(1)  for a water withdrawal referred to in one of subparagraphs a to c of paragraph 1 of section 31.75 of the Act or in section 5 of the Water Withdrawal and Protection Regulation (chapter Q-2, r. 35.2) and with a maximum flow rate of less than 75,000 litres per day: $694;
(2)  for a water withdrawal with a maximum flow rate equal to or greater than 75,000 litres but less than 379,000 litres per day: $1,040;
(3)  for a water withdrawal with a maximum flow rate equal to or greater than 379,000 litres per day: $1,796.
However, where the application for renewal contains modifications to the conditions of operation of a water withdrawal to which section 30 of the Act applies, the fees set out in the first paragraph of section 8 are payable.
M.O. 2015, s. 1; M.O. 2016, s. 8; M.O. 2019-08-28, s. 6.
8.1. The fees for an application for renewal, without modifications, of an authorization referred to in section 8 are as follows:
(1)  for a water withdrawal referred to in one of subparagraphs a to c of paragraph 1 of section 31.75 of the Act or in section 5 of the Water Withdrawal and Protection Regulation (chapter Q-2, r. 35.2) and with a maximum flow rate of less than 75,000 litres per day: $681;
(2)  for a water withdrawal with a maximum flow rate equal to or greater than 75,000 litres but less than 379,000 litres per day: $1,020;
(3)  for a water withdrawal with a maximum flow rate equal to or greater than 379,000 litres per day: $1,762.
However, where the application for renewal contains modifications to the conditions of operation of a water withdrawal to which section 30 of the Act applies, the fees set out in the first paragraph of section 8 are payable.
M.O. 2015, s. 1; M.O. 2016, s. 8; M.O. 2019-08-28, s. 6.
8.1. The fees for an application for renewal, without modifications, of an authorization referred to in section 8 are as follows:
(1)  for a water withdrawal with a maximum flow rate of less than 75,000 litres per day: $681;
(2)  for a water withdrawal with a maximum flow rate equal to or greater than 75,000 litres but less than 379,000 litres per day: $1,020;
(3)  for a water withdrawal with a maximum flow rate equal to or greater than 379,000 litres per day: $1,762.
However, where the application for renewal contains modifications to the conditions of operation of a water withdrawal, the fees set out in the first paragraph of section 8 are payable.
M.O. 2015, s. 1; M.O. 2016, s. 8.
8.1. The fees for an application for renewal, without modifications, of an authorization referred to in section 8 are as follows:
(1)  for a water withdrawal with a maximum flow rate of less than 75,000 litres per day: $666;
(2)  for a water withdrawal with a maximum flow rate equal to or greater than 75,000 litres but less than 379,000 litres per day: $998;
(3)  for a water withdrawal with a maximum flow rate equal to or greater than 379,000 litres per day: $1,724.
However, where the application for renewal contains modifications to the conditions of operation of a water withdrawal, the fees set out in the first paragraph of section 8 are payable.
M.O. 2015, s. 1; M.O. 2016, s. 8.
8.1. The fees for an application for renewal, without modifications, of an authorization referred to in section 8 are as follows:
(1)  for a water withdrawal with a maximum flow rate of less than 75,000 litres per day: $656;
(2)  for a water withdrawal with a maximum flow rate equal to or greater than 75,000 litres but less than 379,000 litres per day: $983;
(3)  for a water withdrawal with a maximum flow rate equal to or greater than 379,000 litres per day: $1,699.
However, where the application for renewal contains modifications to the conditions of operation of a water withdrawal, the fees set out in the first paragraph of section 8 are payable.
M.O. 2015, s. 1; M.O. 2016, s. 8.
8.1. The fees for an application for renewal, without modifications, of an authorization referred to in section 8 are as follows:
(1)  for a water withdrawal with a maximum flow rate of less than 75,000 litres per day: $570;
(2)  for a water withdrawal with a maximum flow rate equal to or greater than 75,000 litres but less than 379,000 litres per day: $855;
(3)  for a water withdrawal with a maximum flow rate equal to or greater than 379,000 litres per day: $1,477.
However, where the application for renewal contains modifications to the conditions of operation of a water withdrawal, the fees set out in the first paragraph of section 8 are payable.
M.O. 2015, s. 1.
8.1. The fees for an application for renewal, without modifications, of an authorization referred to in section 8 are as follows:
(1)  for a water withdrawal with a maximum flow rate of less than 75,000 litres per day: $563;
(2)  for a water withdrawal with a maximum flow rate equal to or greater than 75,000 litres but less than 379,000 litres per day: $844;
(3)  for a water withdrawal with a maximum flow rate equal to or greater than 379,000 litres per day: $1,458.
However, where the application for renewal contains modifications to the conditions of operation of a water withdrawal, the fees set out in the first paragraph of section 8 are payable.